Building Update

After pouring the 2nd story level of concrete on Aug. 4th , the masons prepared the building for the set up of the cinder block walls for the 2nd story of the new building! Masons worked in the early morning hours to try and beat the rising temperatures. They continued to work on the walls all the way up to the unexpected downpour on this morning. Trusses are set to be delivered on Monday the 16th and are to be set as well. We plan on having the job under roof by the end of the month!! Please ccontinue to keep all the workers in your prayers to keep them safe.

2nd Story is well underway!!